CES: Main Site Power Project

Project Summary:

Design and install HV Cable ring main through out the site. Installed new Ring Main Unit and Transformer, all cable containment and radius calculations. Installed HV cable 11,000 volts from existing RMUs through to new RMU.

Key Facts

  • Division: Contract Engineering Solutions
  • Industry: Chemicals & Manufacturing
  • Completion Date:19/06/2019

Conclusion

With two separate supplies now coming into the site, each supply in turn can be closed off for maintenance, allowing the site greater control of the maintence process and reducing downtime. The site is no longer dependent on only the national grid for the supply and with two sources redudency is increased.